Quick answer: to secure a construction site over Christmas, plan the shutdown like a project. Before you lock the gates, check the fencing, remove or immobilise plant, clear high-value materials and fuel, stop hot works and test your alarms and CCTV. Then decide who will watch the site while it is empty: a security guard, mobile patrols or alarm response. Under the CDM 2015 regulations, the principal contractor must make sure steps are taken to prevent unauthorised access, and HSE says that applies outside working hours too.

  • 3 bank holidaysin England and Wales: Fri 25 Dec, Mon 28 Dec (Boxing Day substitute) and Fri 1 Jan
  • 15:51sunset in Manchester in the week before Christmas, so sites are dark before 4pm
  • 2 metresthe height of mesh fence or hoarding HSE suggests for sites in populated areas
USSG security officer using a torch to check the padlock and chain on a locked construction site gate at winter dusk, with a tower crane and a half-built block behind the fence.
Lock every gate before the break, and check each one on every visit while the site is closed.

For most building sites, the Christmas break is the longest time the gates stay shut all year. In Manchester the sun sets at about 15:51 in the week before Christmas, so an empty site can sit in the dark for more than 16 hours a day. Thieves know this too. Plant, tools, fuel, copper cable and materials are left behind, and there may be nobody on site to notice a cut fence until work starts again in January.

This checklist is written by Universal Support Services Group (USSG), an SIA Approved Contractor for security guarding and key holding, based in Stockport. We provide construction site security across Greater Manchester and the North West. Use it to plan your Christmas shutdown, brief your team and decide what level of security cover your site needs.

Christmas shutdown dates 2026

In England and Wales there are three bank holidays over Christmas 2026. Boxing Day falls on a Saturday, so the substitute bank holiday is Monday 28 December. With the weekends either side, many sites will close from Thursday 24 December and reopen on Monday 4 January 2027.

  • Thu24Dec
  • Fri25DecChristmas Day
  • Sat26Dec
  • Sun27Dec
  • Mon28DecBoxing Day (substitute)
  • Tue29Dec
  • Wed30Dec
  • Thu31Dec
  • Fri1JanNew Year’s Day
  • Sat2Jan
  • Sun3Jan
  • Mon4JanScotland only

Bank holiday. Dates from GOV.UK. Christmas Eve and New Year’s Eve are not bank holidays.

Scotland also has a bank holiday for 2 January, moved to Monday 4 January 2027 because 2 January is a Saturday. Northern Ireland has the same Christmas dates as England and Wales. Agree the exact shutdown dates with your client and your security provider early, and book bank holiday cover in good time.

Why construction sites are at risk over Christmas

An empty site with early darkness and no deliveries is an easy target. The main risks we see over the holiday period are:

Christmas shutdown risks on a construction site
RiskLevelWhy it matters over Christmas
Theft of plant, tools and fuelHighSites are empty for days at a time, and thieves know when work stops.
Copper, cable and other metalsHighEasy to carry away and sell. Deliveries left on site before the break are a target.
Arson and fireMediumWaste, timber and fuel near hoardings can be set alight by intruders.
Trespass, including childrenMediumOpen excavations, scaffolds and plant are a serious danger to anyone who gets in.
Weather damage and burst pipesLowerFrost, wind and rain can damage the site, and nobody is there to spot it early.

We cover the wider trend in why construction sites are becoming theft hotspots. CESAR, the national security marking scheme for construction equipment, describes plant and agricultural machinery theft as an estimated £1 million a week problem.

Your legal duties while the site is closed

CDM 2015. Under regulation 13 of the Construction (Design and Management) Regulations 2015, the principal contractor must make sure the necessary steps are taken to prevent unauthorised access to the site. Regulation 15 says a contractor must not start work unless reasonable steps have been taken to prevent unauthorised access, and regulation 18 requires the site perimeter to be signed or fenced off where needed, in line with the risk.

HSE. HSE’s guidance on protecting the public asks you to secure sites when work finishes, isolate and immobilise plant, remove ladders, cover excavations and lock away hazardous substances. In June 2026 HSE reminded construction companies that access must be prevented both during and outside working hours. It also warns that some children see building sites as exciting places to play.

Fire is the other big risk. The Joint Code of Practice on the Protection from Fire of Construction Sites (10th edition, published by the Fire Protection Association) says the site entrance must be locked and secured outside normal working hours, and that the security and fire risk assessments should be reviewed when site works are suspended. It also recommends a continuous fire watch for at least one hour after hot work ends, and keeping combustible waste in a closed, secure skip away from the building. The code is supported by the insurance industry, so check what your own policy requires before the break.

If you are unsure whether your site needs a guard at all, read do construction sites need security guards?

The Christmas shutdown checklist

Work through this list in the last week before the break. Give each section to a named person and sign it off before the gates are locked.

Perimeter and access

  • Walk the full fence line and repair gaps, loose panels and missing clips.
  • Lock every gate with a good-quality padlock and chain, and record who holds each key.
  • Remove ladders and block access to scaffolds, and lock tower crane anti-climb hatches.
  • Put up clear signs with an emergency contact number on the main gate.

Plant, tools and vehicles

  • Return hired plant before the break if you will not need it in January.
  • Park remaining plant inside the compound, with buckets lowered and keys removed.
  • Use immobilisers and wheel clamps, and make sure machines are security marked.
  • Empty vans of tools and lock small plant in a secure container.

Materials, fuel and waste

  • Time deliveries so high-value materials such as copper cable and pipe do not arrive just before the break.
  • Store fuel in locked bowsers or tanks and keep the levels low.
  • Clear skips and combustible waste away from buildings and hoardings.
  • Isolate gas bottles and store them in a locked, ventilated cage.

Fire and services

  • Stop hot works well before the site closes and complete the fire check.
  • Isolate water and gas where you can, but keep power to alarms, CCTV and lighting.
  • Check that fire points and extinguishers are in place and not tampered with.
  • Agree who the fire service should contact if there is a fire on site.

Alarms, CCTV and lighting

  • Test intruder alarms, CCTV towers and remote monitoring before you leave.
  • Check that cameras cover gates, compounds and the plant yard, and that recording works.
  • Set security lighting on timers or sensors, especially for the long dark evenings.
  • Confirm the alarm receiving centre has the right keyholder contacts.

People and contacts

  • Name at least two keyholders and check their numbers work over the holidays.
  • Agree who will attend an alarm and how quickly, without sending staff alone.
  • Brief neighbours and let them know who to call if they see anything.
  • Leave the security company the site plan, access codes and a list of plant on site.

Tip: Register plant on a national database such as CESAR, the Construction Equipment Association’s marking scheme, and keep a list of serial numbers. Secured by Design, the police crime prevention initiative, recommends both, and police can check CESAR-marked machines if they are stolen.

USSG security officer shining a torch through a locked mesh compound at an excavator with its bucket lowered and a site dumper, with a CCTV tower behind, on a wet night.
Park plant inside a locked compound, with buckets lowered and keys removed.

A four-stage Christmas security plan

  1. Two to three weeks beforePlan and book coverDecide which plant stays on site, agree the security level with your client and insurer, and book guards or patrols early so bank holiday cover is in place.
  2. Last working dayLock up properlyWork through the checklist, photograph the site, lock the compound and hand the security team the keys, site plan and contact list.
  3. During the shutdownWatch and respondGuards or patrols check the fence line, gates, compounds and plant, and report after every visit. Alarms and CCTV alerts go to someone who can attend.
  4. Restart dayCheck before work startsWalk the site before the workforce arrives, compare it with your lock-up photos and report any damage or losses straight away.
Infographic: four-stage Christmas shutdown security plan for a construction site, from planning and lock-up to patrols during the break and checks on restart day.
Plan the shutdown like any other phase of the project.

Guards, mobile patrols or alarm response?

There is no single answer. The right cover depends on the size of the site, what is left on it, the neighbourhood and the risk your insurer and client will accept. Many sites combine two or more of these.

Christmas security options for construction sites
OptionWhat you getBest forLearn more
Static security guardSomeone on site day and night, or during set hoursLarge or high-value sites, sites near housing, sites with plant that cannot be removedConstruction site security
Mobile patrolsVisits at set or random times, with a report after each checkSmaller sites, sites with good fencing and CCTV, budgets that cannot cover a full-time guardMobile patrol security
Key holding and alarm responseA licensed officer attends when the alarm or CCTV is triggeredSites with monitored alarms or CCTV towers that need someone to respondKey holding and alarm response
CCTV and remote monitoringCameras watched by a monitoring centre, with audio warningsA useful layer on most sites, ideally backed by patrols or alarm responseCCTV services

Whatever you choose, check that the company and its officers hold the right SIA licence. Guarding premises and key holding under a contract are licensable activities, and the Joint Code of Practice on fire says guards should be SIA licensed and come from an Approved Contractor or a company with equivalent approval. For typical hourly rates, see our guide to security guard costs in the UK. Ask for bank holiday rates in writing before you book.

A good security report should show the time of each check, which gates and compounds were checked, photos of anything unusual and what action was taken. If a patrol finds a broken fence on 27 December, you want to know that day, not on 4 January.

USSG mobile patrol officer checking the fence line of a closed construction site with a torch and recording the visit on a tablet, next to a USSG patrol car on a frosty winter night.
A patrol report should show the time of each check and anything found.

Restart day: checks before work resumes

  • Walk the whole site before the workforce arrives and compare it with your lock-up photos.
  • Check fencing, gates, cabins and containers for damage or signs of entry.
  • Count plant, tools and high-value materials against your list.
  • Carry out the usual pre-use inspections of scaffolds, excavations and plant before anyone uses them, especially after storms or frost.
  • Report any theft to the police straight away and get a crime reference number for your insurer.
  • Review the security reports from the break and agree what to change for next year.

Construction site security in Stockport and Greater Manchester

USSG is based at Houldsworth Mill in Reddish, Stockport. We provide security guarding, mobile patrols and alarm response for construction sites across Stockport, Manchester, Salford, Trafford, Oldham, Bury and the wider North West. Read how we approach construction site security in Manchester, or see our security services in Stockport.

If you need Christmas cover for a site, call us on 0330 341 2124 with the site postcode, the shutdown dates and what will be left on site.

Frequently asked questions

When is the Christmas shutdown for construction sites in 2026?

In England and Wales the bank holidays are Friday 25 December, Monday 28 December (the substitute day for Boxing Day) and Friday 1 January 2027. With the weekends, many sites close from Thursday 24 December to Sunday 3 January. Scotland also has a bank holiday on Monday 4 January 2027.

Who is responsible for construction site security over Christmas?

Under the CDM 2015 regulations, the principal contractor must make sure steps are taken to prevent unauthorised access to the site, and contractors have duties too. HSE says access must be prevented outside working hours as well, so the duty continues while the site is closed. Agree in writing who arranges security for the break.

Do I need a security guard on site over Christmas?

Not always. A smaller, well-fenced site with CCTV may manage with mobile patrols and alarm response. Large sites, sites with high-value plant or materials, and sites next to housing often need a guard. Your client or insurer may also set requirements.

How can I stop plant theft over Christmas?

Return hired plant you will not need, lock remaining machines in a compound, remove keys and use immobilisers. Register plant on a national database such as CESAR and keep a list of serial numbers. Secured by Design, the police crime prevention initiative, recommends all of these steps.

What should a Christmas shutdown checklist include?

Fencing and gates, ladders and scaffolds, plant and tools, fuel and high-value materials, waste and hot works, alarms, CCTV and lighting, keyholder contacts and a restart-day plan. Give each section to a named person and sign it off before the site closes.

Do construction site security guards need an SIA licence?

Yes. Guarding premises or property under a contract is a licensable activity, so officers supplied by a security company need a front-line SIA licence. The Joint Code of Practice on fire prevention also says site guards should be SIA licensed.

What should I check when the site reopens in January?

Walk the site before the workforce arrives and compare it with your lock-up photos. Count plant and materials, check fencing and cabins for damage, and inspect scaffolds and excavations before anyone uses them. Report any theft to the police and your insurer straight away.